Over 6,000 tons less carbon dioxide!
Grupa Azoty FOSFORY has launched an investment involving the exchange of energy resources. After the modernization of the existing combustion nodes and adaptation of the installation to gas supply, the emission of greenhouse gases to the atmosphere will be significantly reduced.
The cost of the task is PLN 10 million. The Provincial Fund for Environmental Protection and Water Management in Gdańsk granted a loan of PLN 8 million for the gasification of two production lines.
The implementation of the investment will bring savings of approximately PLN 1 million per year.